Flex schedule watered on a non-scheduled day - comments!

Can’t say this ever happened before but I have Wednesday excluded from a Flex Schedule program and it ran anyways today, Wednesday! Nothing seems off otherwise - date, settings, etc. Any comments? Should I reboot the controller?

Thanks

Craig

@MonitoringPost

Good question. I looked at the flex audit information and it is showing that our processing rules are working.

We aren’t allowed to water today based on the flex schedule rule

So, we didn’t explicitly tell the controller to run flex this morning.

This could be due to a hardware change we made on August 30th that under powered the flex processing engine, hence sending the flex schedule on August 30th, but after its scheduled run time. The flex schedule still lived on the controller but ultimately ran at the correct time the next day.

We’ve since reverted the hardware change.

If you see any other issues please let us know.