Flex Daily running two zones at once

I’ve noticed that Flex Daily has recently started running two zones at once on my schedule. Is this intended? Can I prevent it?

Notice the 2 under the 6/3 schedule.

Thanks!

Brad

Took awhile to see what was going on. The schedule with frontyard zones started Tuesday 6/2 at 8pm and finished Wednesday 6/3 at 2:14am. The schedule with backyard zones started Wednesday 6/3 at 8pm and finished Wednesday 6/3 at 11:49pm.

They both look like they started at the same time, but actually started at the same time on different days but both finished on Wednesday.

If you look under History it will show a better sequential representation.

:cheers:

Thanks for the quick reply and explanation. So if I see a day that has a 2 indicated like my second screen shot - that represents the scenario you described?

Yeah, the reporting day is on the day it finished watering.

:cheers:

Thanks!