Water Budget Problem

I just had my first Water Budget update applied. No problem with that, except…

I have two schedules that were affected. Both contain more than one zone. Only the FIRST zone was updated. The others were not. I have left them as they are if someone wants to look at them. I’ll update them manually soon.

David

I’ve a schedule that similar. 4 of 5 zones were changed, the last was not. However, the run time on the last zone is only 6 minutes, the first zones went from 45 to 43 minutes.